INSTALLATION TIPS
-The HTS-11 system must be used as a unit (i.e. high temperature bowl, head and cartridge)
-Install vertically using the mounting bracket provided
-Use 3/4″ water line and observe proper inlet/outlet water directions
-Some pressure relief mechanism should be provided downstream of the system to permit releasing line pressure when changing cartridges
-Deliming of equipment prior to installation is recommended, but not required
OPERATION TIPS
-Inspect HT-10 cartridge at least every 6 months for replacement
-Pre-existing equipment scale may be dislodged and settle to the bottom of a chamber which can clog drain initially. Remove any settled scale
-In new installations, the HydroBlend usage rate may start high, but will be reduced as existing scale is removed
-Replace HT-10 cartridge before HydroBlend compound is completely used up
APPLICATION or SIZING
-Commercial dishwashers
-Commercial glassware washers
-Warewashing booster heaters